Transmission Element :

Construction of 400kV D/C: Khandukhal (Srinagar)- Rampura (Kasshipur) Transmissin line (*TWIN HTLS) -194km approx.

1x80 MVAr Switchable line reactor at Rampura (Kashipur) end on each circuit of Khandukhal (Srinagar) – Rampura (Kashipur) line.
• Switching equipment for 42 kV 80 MVAR switchable line reactor -2nos.
• 420 kV, 80 MVA r Switchable line reactor -2 nos.

1 no. of 400kV line bay at Rampura (Kashipur) S/s
• 400kV line bay -1 no.

Upgradation of existing 400V bays at Khandukhal (Srinagar)
• Upgradation works for 400kV line bays -2nos.

Upgradation of existing 1 no. of 400kV diameter comprising line bay and ICT bay along with associated Tie Bay at Rampura (Kashipur)
• Upgradation works for 400kV line bay -1 no.
• Upgradation works for 400kV ICT bay -1 no.
• Upgradation of Tie Bay – 1no

Project Details :

Project Location : Uttarakhand & Uttarapradesh

Regulator : Central Electricity Regulatory Commission

Nodal Agency : Central Transmission Utility of India Ltd

Concession / TSA Term : 35 years

Project Mode : Tariff Based Competitive Bid

Project Type : Inter State

Project meant : Generation linked project – to evacuate power from Pipalkoti & Tapovan HEP

Business Model : Build Own Operate Maintain

CERC Petition : CERC Petiton

Final Licence Petition : Final Licence Petiton

Press Notice : Times Nation